01.06.2011
Tests on the channel for the for the shielding of power lines underground were completed.
Tests have allowed us to optimize the G-iron configuration in order to mitigate the induction, generated by a set of three conductors in clover paths by a phase current of 1600 A.
Below the first part of the final report (on request can be sent the integral version) and the final graph in shielded field.
Test lasted for 6 days (1600 detections) in which 6 possible G-iron configurations have been tested, with the aim to obtain a residual induction of 3 µT at a distance of 1,50 meters measured perpendicular by the raceway.
Tests have shown that an hybrid configuration guarantees a good performance/price ratio without need of more expensive configurations. More specific in product section.